NVIDIA GB200 Chip Mass Production Halted, Delayed to 2025

Recently, NVIDIA's next-generation Blackwell architecture chip, the GB200, has encountered technical bottlenecks in its mass production plans, garnering widespread attention in the industry. As a representative of high-performance computing chips, the production halt of the GB200 has not only affected NVIDIA itself but also impacted its key clients, including Microsoft.

 

NVIDIA GB200 Faces Production Challenges Again

It has been reported that the GB200 chip has encountered significant issues in the design of the backplane connection. The plug-in connectors provided by Amphenol, a Tier-1 supplier in the United States, have underperformed in testing, with yields failing to meet expected levels. This issue may delay the mass production schedule of the GB200 chip until March 2025. Additionally, the significant specification upgrades of the GB200 chip have increased production complexity, further leading to low yields and test failures.

NVIDIA is actively seeking alternative suppliers to address these issues, but patent restrictions and delays in capacity expansion are expected to prolong the resolution process. NVIDIA is even exploring alternative designs, including the production of a single-GPU version of the Blackwell chip, to accelerate delivery.

 

Impact of GB200 Production Delay on NVIDIA

The delayed mass production of the GB200 will undoubtedly impact NVIDIA. Firstly, the postponement of the release means that NVIDIA will not be able to generate revenue from the sales of this high-performance chip in a timely manner, directly affecting its short-term revenue growth. Moreover, NVIDIA may need to invest more R&D resources and funds to solve the current technical challenges, further increasing its operating costs.

At the same time, in the fields of high-performance computing and artificial intelligence, market competition is exceptionally fierce. NVIDIA's main competitors, such as AMD and Intel, are also continuously launching new generations of products. The delayed mass production of the GB200 may put NVIDIA at a competitive disadvantage, potentially losing some market share.

More importantly, the delayed mass production of the GB200 has already affected NVIDIA's relationship with its major client, Microsoft. If NVIDIA fails to resolve the production issues in a timely manner, it may further impact its relationships with existing clients and even future cooperation opportunities.

 

Impact on NVIDIA's Clients and Partners

As one of NVIDIA's major clients, Microsoft originally had a strong demand for the GB200 chip. However, due to the delay in the mass production schedule and yield issues, Microsoft has had to cut about 40% of its orders and allocate some to the GB300, which is scheduled for release in mid-2025. This move reflects Microsoft's concerns about the uncertainty of the GB200 chip's mass production and is also an adjustment to its own supply chain management.

In addition to NVIDIA and Microsoft, this incident also involves other related companies. For example, Amphenol, a Tier-1 supplier providing connectors for the GB200 chip, has become one of the bottlenecks in mass production due to poor product yields. Furthermore, TSMC, as the foundry for the GB200 chip, has also been affected by this incident. TSMC's advanced CoWoS-L packaging technology, while delivering high performance, has also increased the complexity and difficulty of production.

 

Conclusion

NVIDIA GB200 Chip Mass Production Halted, Delayed to 2025.jpgThe halted mass production of NVIDIA's GB200 chip once again highlights the complexity and uncertainty of the high-tech industry's supply chain. In the face of technical bottlenecks and market changes, companies need to respond flexibly and actively seek solutions. For NVIDIA, resolving the mass production issues and improving chip yields will be a key focus of its future work. For clients like Microsoft, it is also necessary to closely monitor supplier dynamics and prepare corresponding risk mitigation measures.

 

ConevoICs Distributor

Conevo is an independent ic component distributor offering a wide range of ic chips such as PLDS, operational amplifiers, embedded ics, memory, sensors, computing components, and more. In addition, Conevo also offers NVIDIA’s A100, H100 GPUs models, as well as NVIDIA AD102-300-A1 and AD102-301-A1 GPUs models, and more computer components from other technology brands, please click Conevo to contact or view more information.

Website: www.conevoelec.com

Email: info@conevoelec.com

Contact Information
close